Planned Outages
During the year, BritNed takes planned outages to carry out essential maintenance activities. During these periods, capacity will not be offered. Any auctions listed above that have a product period which overlaps the planned outage will include a reduction period in the capacity offered.
| Start (CET/CEST) | Finish (CET/CEST) | Capacity (M/W) |
|---|---|---|
| 12 May 2025 06:00 | 16 May 2025 23:00 | 0 |
| 15 September 2025 06:00 | 21 September 2025 23:00 | 0 |
| 11 May 2026 06:00 | 15 May 2026 23:00 | 0 |
| 6 September 2026 07:00 | 20 September 2026 00:00 | 0 |