BritNed Milestones
1999
Start BritNed feasibility study
March 2000
Ready first economic study
October 2000
Ready feasibility study
20 October 2001
Establishment BritNed Development Ltd.
Summer 2003
Offshore seabed survey
April 2005
Completion environmental impact studies
2007
Awarded contracts to construction partners
2008
Manufacturing of cables and electrical equipment Environmental mitigation
May 2008 – December 2010
Construction of converter stations
September 2009 – October 2010
Cable installation
February 2010 – December 2010
Development of explicit trading platform with Unicorn SystemsDevelopment of implicit auction model with APX-ENDEX
October 2010 – March 2011
Testing performance cable and trading platforms
24 March 2011
First explicit auction
31 March 2011
First implicit auction
1 April 2011
BritNed operational